Whatever your position in an international letter of credit transaction, whether you are an export specialist in a small manufacturing company, an import responsible in a medium size international trade firm or a trade finance expert in one of the first class banks, you should always be very careful with the dates of the documents.

The dates of the documents are one of the major sources of discrepancies. This is not only my claim, but also supported by evidences.

Significant amount of ICC Opinions are issued related to this subject for the last 25 years.

How to Deal with Dates of the Documents When Working with a Letter of Credit?

Make Sure That Each Document is Properly Dated: As a general rule each letter of credit document should be dated. The documents are expected to be dated after the issuance date of the credit, but not later than the presentation date.

Important Note: The letter of credit rules allow presentation of undated documents.

Additionally, documents dated prior to the issuance date of the credit is also acceptable under the letters of credit rules.

However, the issuing banks prevent presentation of such documents via additional conditions such as:

  • All documents including transport documents must be dated but not dated prior to the issuance date of this credit.
  • All required documents date should be later than issue date of this later of credit
  • All documents must be dated and made out in English language

Follow the Instructions Indicated in the Letter of Credit: Some of the letters of credit may contain special conditions regarding the dates of the documents such as:

  • Shipment dated before 16/11/2018 not acceptable (blocking regulatory condition).
  • First shipment is to be effected on or before 50 days from L/C issuance date.

If the letter of credit contains a clause as indicated above, the beneficiaries must act accordingly.

Make Sure That You are Using L/C Terminology Correctly: Some word have special meanings under the letter of credit rules such as:

  • The term “within” when used in connection with a date excludes that date in the calculation of the period.
  • within 2 days after” indicates a period from the date of the event until 2 days after the event.
  • not later than 2 days after” does not indicate a period, only a latest date. If an advice must not be dated prior to a specific date, the credit must so state.
  • at least 2 days before” indicates that something must take place not later than 2 days before an event. There is no limit as to how early it may take place.
    within 2 days of” indicates a period 2 days prior to the event until 2 days after the event.

Special Suggestions From the International Standard Banking Practice – ISBP 2007

  • Drafts, transport documents and insurance documents must be dated even if a credit does not expressly so require.
  • Documents must not indicate that they were issued after the date they are presented.
  • Any document, including a certificate of analysis, inspection certificate and pre-shipment inspection certificate, may be dated after the date of shipment. However, if a credit requires a document evidencing a pre-shipment event (e.g., pre-shipment inspection certificate), the document must, either by its title or content, indicate that the event (e.g., inspection) took place prior to or on the date of shipment.
  • A document indicating a date of preparation and a later date of signing is deemed to be issued on the date of signing.
  • Dates may be expressed in different formats, e.g., the 12th of November 2007 could be expressed as 12 Nov 07, 12Nov07, 12.11.2007, 12.11.07, 2007.11.12, 11.12.07, 121107, etc. Provided that the date intended can be determined from the document or from other documents included in the presentation, any of these formats are acceptable.
  • To avoid confusion it is recommended that the name of the month should be used instead of the number.

What Does Latest Date of Shipment and Expiry Date Mean in a Letter of Credit?

Latest Date of Shipment and Expiry Date

On this post, you can find explanations regarding the latest date of shipment and expiry date.

If a letter of credit requests presentation of a transport document and a latest date of shipment indicated in the credit; then the shipment must be completed on or before the latest date of shipment indicated in the credit.

If a letter of credit requests presentation of a transport document but not indicated a latest date of shipment; then the shipment and the presentation must be completed on or before the expiry date indicated in the credit.

According to the letter of credit rules, a presentation including one or more original transport documents subject to articles 19, 20, 21, 22, 23, 24 or 25 must be made by or on behalf of the beneficiary not later than 21 calendar days after the date of shipment as described in these rules, but in any event not later than the expiry date of the credit.

Latest Date of Shipment:

  • Latest date of shipment is an optional information and not every letter of credit issued in swift format contains a latest date of shipment.
  • Latest date of shipment can be meaningful only if the letter of credit requests presentation of a transport document. No transport document, no meaning of the latest date of shipment.
  • If the letter of credit indicates a latest date of shipment, then the beneficiary has to complete the shipment of goods on or before this date.
  • The beneficiary has to present a transport document showing a shipment date on or before the latest date of shipment in order to prove his compliance with the latest date of shipment.
  • If the beneficiary presents a transport document showing a shipment date later than the latest date of shipment, then the issuing bank raises a “late shipment discrepancy“.

Expiry Date :

  • The beneficiary has to present the documents to nominated bank on or before the expiry date of the l/c.
  • If the beneficiary can not make the presentation on time, the letter of credit will be terminated and will not be valid any more.